Glencoe Public Library:
Rooted in History, Building for Tomorrow.

Key Details

Budget


$17.3 million

Funding Sources


A combination of existing library reserves, funds raised through a capital campaign, private donations, grants, a loan, and a bond referendum

Project Timeline


2024

February — The Library Board issues a Request for Qualifications for Architectural Services. 18 responses were received, and three finalists were selected by the Library Board.

May — Skidmore, Owings & Merrill (SOM) is awarded the architectural services contract to complete a master space plan.

October — The Library Board and SOM present the preliminary master space plan to the community.

December — The modified master space plan is approved by Library Board.


2025

March — The Library Board hires Just Cause Consulting to help launch a capital campaign to help finance the renovation project.

September — The Village of Glencoe Zoning Commission will entertain a Special Use Permit for the proposed library renovation’s large program and community room.

September — The Village of Glencoe Plan Commission will conduct an external appearance review of the proposed library renovation.

November — The Village of Glencoe Board of Trustees will entertain accepting the Library Board’s pursuit of a bond to finance the library renovation.


2026

March 17 — The target date for the bond referendum. The amount sought will depend on the success of prior fundraising efforts.

Autumn/Winter — The target for construction to begin.


2028

December — The target date for project completion.